top of page
Writer's pictureSeema Iyer

Introduction to SAP ERP Production Planning and Manufacturing (PP) Certification Practice Exam Exam

Production Planning and Manufacturing (C_TSCM42_67) preparation guide helps you to get focused on exam. This guide also helps you to be on C_TSCM42_67 exam track to get certified with good score in the final exam.



C_TSCM42_67 Production Planning and Manufacturing Exam Summary


Exam Name: SAP Certified Application Associate – Production Planning & Manufacturing with SAP ERP 6.0 EHP7

Exam Code: C_TSCM42_67

Level: Associate

Exam Price: $550 (USD)

Duration: 180 mins

Number of Questions: 80

Passing Score: 63%

Reference Books: TSCM40, TSCM42

Schedule Exam: SAP Training OR Pearson VUE


Exam Syllabus: C_TSCM42_67 SAP ERP Production Planning and Manufacturing (PP) Certification Practice Exam


1. Material and Capacity Requirements Planning (>12%)

Characterize production-relevant planning functionality.

Books: SCM240, SCM365


2. Material Requirements Planning (PP-MRP) (>12%)

Explore material requirements planning functions.

Books: SCM240


3. Production Orders Advanced (PP-SFC) (>12%)

Configure production order functionality.

Books: SCM310


4. Lean Manufacturing (PP-REM, PP-KAB) (8% - 12%)

Outline the highlights of repetitive manufacturing and kanban.

Books: SCM300, SCM130


5. Master Data (LDM) (8% - 12%)

Set up master data for production planning and manufacturing.

Books: PLM114


6. Production Orders Basics (PP-SFC) (8% - 12%)

Apply production order functionality.

Books: SCM310


7. Application Overview and Background (< 8%)

Characterize the interplay of master data, planning, ATP, and production functionality.

Books: TERP50, SCM240, SCM300, SCM130


8. Basics on SAP Business Processes (E-Learnings) (< 8%)

Outline the scope of SAP SCM business processes.

Books: TERP01, TERP50


9. Process Orders (PP-PI) (< 8%)

Identify specific properties of process orders.

Books: SCM300, SCM130


SAP C_TSCM42_67 Certification Sample Questions and Answers


To make you familiar with Production Planning and Manufacturing (C_TSCM42_67) certification exam structure, we have prepared this sample question set. We suggest you to try our Sample Questions for PP C_TSCM42_67Certification to test your understanding of SAP

C_TSCM42_67process with real SAP certification exam environment.


C_TSCM42_67Production Planning and Manufacturing Sample Questions:-


01. Which objects can affect the calculation of capacity requirements for an operation?

Note: There are 3 correct answers to this question.


a) Standard values (routing)

b) In-house production time (material master)

c) Transport time (routing)

d) Formulas (work center)

e) Operation control key (routing)


02. A user of the SAP ECC system wants a rolling planning time fence (firming type = 1) to be set up for a material; in other words, new planned orders are firmed within a planning time fence. When an unforeseen production failure occurs, it can happen that such firmed planned orders are not being processed because time passes. What solution would automatically delete firmed planned orders?

Note: Please choose the correct answer.


a) In the material master, an MRP type is used in which the roll-forward mechanism is activated (Customizing for requirements planning).

b) The demand adjustment activated in the Customizing for demand adjustment is used.

c) Firmed planned orders can only ever be deleted manually because of the header data firming.


03. In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type Pd) The number in each of these alternatives represents a firming type.

What does a firming type define?

Note: There are 2 correct answers to this question.


a) Handling existing procurement proposals outside the planning time fence.

b) Handling existing procurement proposals within a planning time fence.

c) Handling new requirements within the planning time fence.

d) Handling new procurement proposals that need to be created due to new requirements within the planning time fence.


04. What options does the SAP ECC system offer to retrieve the available capacity for work centers?

Note: There are 3 correct answers to this question.


a) Attendance list

b) Standard available capacity

c) Shift plan

d) Interval of available capacity

e) Shift sequence


05. Which of the following master data can be used with process orders?

Note: There are 3 correct answers to this question.


a) Serial numbers

b) Master recipes

c) Resources

d) Production/resource tools

e) Production versions


06. Which of the following organizational units does the manufacturing, planning, and execution process use?

Note: There are 2 correct answers to this question.


a) Storage Location

b) Sales Area

c) Purchase Organization

d) Plant


07. You want to enhance the system statuses of a production order with user statuses. How do you do this?

Note: Please choose the correct answer.


a) Define the user statuses in the order type-dependent parameters.

b) Define a status profile in Customizing and assign it to the production scheduling profile.

c) Define a status profile in Customizing and assign it to the order type.

d) Define the user statuses in the Customizing table of the system statuses.


08. You enter a new BOM (Bill of Materials) in SAP ECC but forget to enter a plant reference. Which of the following statements describes what happens when you try to save it?

Note: Please choose the correct answer.


a) When saving the BOM, a group BOM is created which can, under certain conditions, be assigned to a plant later.

b) When saving the BOM, a dialog box appears prompting the user to enter a plant.

c) When saving the BOM, an error message appears stating that it is not possible to save a BOM without a plant reference.

d) When saving the BOM, a warning message appears. In the corresponding dialog box, it is possible to create a plant-specific engineering BOM.


09. You want to use the different options for planning in SAP ECC. What is the correct sequence of the planning procedures?

Note: Please choose the correct answer.


a) Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planning

b) Demand management -> Sales and operations planning -> Capacity planning -> Long-term planning -> Material requirements planning

c) Material requirements planning -> Demand management -> Sales and operations planning -> Long-term planning -> Capacity planning

d) Long-term planning -> Sales and operations planning -> Demand management -> Material requirements planning -> Capacity planning


10. In the SAP ECC system, you interpret the result of a routing schedule. When scheduling a routing in the SAP ECC system which of the following time elements are interoperation times?

Note: There are 2 correct answers to this question.


a) Safety time

b) Floats before and after production

c) Processing time

d) Move time



Solutions:


QUESTION: 01- Answer: a, d, e

QUESTION: 02- Answer: a

QUESTION: 03- Answer: b, d

QUESTION: 04- Answer: b, d, e

QUESTION: 05- Answer: b, c, e

QUESTION: 06- Answer: a, d

QUESTION: 07- Answer: c

QUESTION: 08- Answer: a

QUESTION: 09- Answer: a

QUESTION: 10- Answer: b, d

444 views0 comments

Comments


bottom of page